Monterey Regional Water Pollution Control Agency  
MONTEREY REGIONAL WATER POLLUTION CONTROL AGENCY
"Turning Wastewater into Safe Water"
 
 

 

Current and Future Projects

Current Projects
Reeside Pump Station Odor Scrubber & Electrical Upgrades Reeside Pump Station Odor Scrubber & Electrical Upgrades
The Reeside Pump Station is located adjacent to San Carlos Beach in Monterey. This project will result in the construction of an odor control system and electrical upgrades for the Reeside Pump Station. Design was performed by Brown and Caldwell. Blocka Construction will install the equipment. Contact Garrett Haertel at (831)883-6176 for more information.
Reeside Pump Station Electrical Upgrades
Installation of temporary power and controls, demolition of existing Motor Control Centers (MCCs), Main Breaker Panel, and wiring and installation of new electrical service panel, MCCs, and controls. A construction contract has been awarded to Blocka Construction. Contact Garrett Haertel at (831) 883-6176 for more information.
Fire Alarm System Upgrades
The design and upgrade of the fire alarm system at the Regional Treatment Plant to meet or exceed the requirements of NFPA 72. It is anticipated that the construction of this project will be awarded at our May Board meeting. Contact Jerry Valladao at (831) 883-6179 for more information.
Coral Pump Station Improvements Coral Pump Station Improvements
This project will rehabilitate the pump station's concrete structure and will include the following: removing and replacing the concrete lid with a new precast concrete lid, rehabbing the support structure, concrete curb, and existing concrete slab, and demolition and removal of existing abandoned generator exhaust piping. Anderson Pacific Engineering Construction has been awarded the construction contract for this project. It is anticipated that the construction will be from May 29th through June 8th. Contact Jerry Valladao at (831) 883-6179 for more information.
Digester Gas Projects
This project will implement upgrades to the Digester Gas Waste Burner Automation System as well as new piping for the High Pressure Storage sphere. It is anticipated that this project will be awarded to Anderson Pacific Contruction Inc. at our May Board meeting. Please contact Jennifer Gonzalez at (831) 883-6172 for more information.
Seismic Evaluations
The Regional Treatment Plant has several concrete block structures with wood frame roofs that require seismic assessment to ensure adequate connections under the current seismic codes. The draft report was recently completed by Carollo Engineers. Implementation of the recommendations will begin next Fiscal Year. Please contact Jerry Valladao at (831) 883-6179 for more information.
Bioflocculation Aeration System Upgrades
This project will upgrade the blowers and diffusers that were originally installed in the early 1990's at the Regional Treatment Plant. It is anticipated that this project will be awarded to Overaa Construction at the May Board Meeting. For more information on this project please contact Tom Kouretas at (831) 883-6178.
Digesters #2 and 3 Mixing System Replacements Digesters #2 and 3 Mixing System Replacements
In 2006, the gas mixing system on Digester #4 was replaced with a higher efficiency pump mixing system. In 2009 the design was completed for installation of two more pump mixing systems on Digesters #2 and 3. This project will construct the improvements to those two digesters. It is anticipated that a construction contract will be awarded to Overaa Construction at our May Board Meeting. Please contact Jerry Valladao (831) 883-6179 for more information.
Future Projects
RTP Roofing Projects RTP Roofing Projects
Several metal roofs at the Regional Treatment Plant have experienced significant corrosion and need to be replaced. This project will replace the roofs at the Maintenance Building, Administration Building, and Chemical Building as well as gutters on miscellaneous buildings throughout the plant. A construction contract for this work has been awarded to Petersen Dean Roofing. Please contact Jennifer Gonzalez at (831) 883-6172 for more information.
Castroville Pump Station Influent Manhole and Sluice Gate Vault Coating Projects Castroville Pump Station Influent Manhole and Sluice Gate Vault Coating Projects
The influent manhole to the Castroville Pump Station has deteriorated significantly due to high H2S levels from the Moss Landing and Castroville influent pipeline flows. A new manhole will be constructed with a coating to combat future deterioration. The influent sluice gate vault to the Castroville Pump Station contains grinders and sluice gates to isolate the pump station in an emergency. The sluice gate vault will be coated to ensure that concrete deterioration is minimized or eliminated. Please contact Jerry Valladao at (831) 883-6179 for more information.
 

 

Administration Offices
5 Harris Court, Bldg D, Monterey, CA 93940 | (831) 372-3367 or (831) 422-1001 | Fax: (831) 372-6178
Regional Treatment Plant
14811 Del Monte Boulevard , Marina, CA 93933 | (831) 883-1118 or (831) 424-1108 | Fax (831) 883-0516

Copyright © 2012 MRWPCA. All Rights Reserved.
Board of Directors Public Meetings MRWPCA Steff Employment Opportunities Contact MRWPA